Financial Number: 419345-2-52-01
Project Length: 7.2-miles
Project Limits: State Road 80/Southern Boulevard, from west of Lion Country Safari Road to Forest Hill Boulevard/Crestwood Boulevard
Start Date: July 2018
Completion Date: Early 2022.
Contractor: Community Asphalt Corp.
Estimated Construction Cost: $33 million
Scope of Work: Work includes widening the existing roadway from four to six lanes, adding a 12-foot shared-use pathway on the north side of the roadway, adding bike lanes, milling and resurfacing, drainage improvements, adding lighting and signalization, installing curb and gutter, guardrails, minor median modifications and signage and pavement markings.
Click here for upcoming lane closures
|