US-1/Federal Highway between Gulfstream Boulevard and Bamboo Lane

Financial Number: 450604-1-52-01

Project Length: 0.569 Miles

Project Limits: U.S. Highway 1 (US-1)/Federal Highway between Gulfstream Boulevard and Bamboo Lane

Project Purpose: This project will improve safety and nighttime visibility by providing street lighting on existing and proposed Florida Power and Light (FPL) poles along the corridor.

Poles Installation:

  • Proposed Start Date: July 2024

  • Proposed Completion Date: August 2025

Retrofit Poles:

  • Proposed Start Date: July 2024

  • Proposed Completion Date: November 2024

Estimated Construction Cost: $158,707

Scope of Work:

  • Filling in the gap to existing lighting along US 1/Federal Highway from Gulfstream Boulevard to Bamboo Lane
  • Installation of new luminaires and retrofitting of existing luminaires on joint use FPL poles on the West side of US 1/Federal Highway
  • Installation of new FPL Stand Alone Light Poles on the East side of US 1/Federal Highway

Construction Impacts:

  • Lane closures will take place during off-peak hours
  • Access to businesses and residential properties will be maintained at all times during construction

Point of Contact:

Project Photos

Pre-Construction

Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone
zero