Financial Number:
406919-1-52-01
Project Length: 0.95 miles
Project Limits: CSX railroad bridge over the south fork of the New River
Start Date: October 28, 2013
Completion Date: August 18, 2017
Contractor: Johnson Bros. Corp. of Southland
Estimated Construction Cost: $22 million
Scope of Work: Project improvements include replacing the CSX railroad bridge over the south fork of the New River.