Financial Number:
424671-1-52-01
Project Length: 3.64 miles
Project Limits: Dixie Highway Roadway from McNab Road to NE 26 Street
Start Date: January 6, 2014
Completion Date: February 11, 2015
Contractor: Community Asphalt
Estimated Construction Cost: $3.9 million
Scope of Work: Project improvements included removing old asphalt and repaving Dixie Highway within the project limits, upgraded existing traffic signals to mast arms at NE 34th Court and Oakland Park Boulevard, upgraded pedestrian features including curbs and ramps to meet ADA standards, improved drainage, and installed new vehicle and pedestrian railing on Middle River Canal bridge.