FDOT District Four - Broward County Header Image

SR 7/US 441 and SR 858/Hallandale Beach Boulevard Transit Improvements Project

Financial Number: 429576-2-52-01, 02, 03, 04 /441772-1-52-01

Project Length: 22 miles

Project Limits: SR 7/US 441 from the Broward / Miami-Dade County Line to North of Sample Road and SR 858/Hallandale Beach Boulevard from Edmund Road to SW 58 Avenue

Start Date: April 14, 2022

Completion Date: January 11, 2024

Contractor: Weekly Asphalt Paving, Inc.

Estimated Construction Cost: $4,581,957

Scope of Work:
Project improvements include: upgrading pedestrian signals with countdown timers and converting the existing lighting to LED along SR 7/US 441 at 23 intersections; adding a signalized, pedestrian mid-block crossing at the intersection of SR 7/US 441 and NW 3 Street; installing a 7-foot bicycle lane along westbound SR 858/Hallandale Beach Boulevard; widening the roadway to accommodate bicycle lanes along SR 7/US 441 from Southgate Boulevard to Cypress Creek Greenway/C-14 Canal; upgrading sidewalks and curb ramps at 23 intersections

Documents:

PDF IconProject Flyer SR 7 Hallandale Beach Transit Project

Point of Contact:

"Para información y preguntas en Español, por favor llame al (954) 777-4302."

 

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

 

During Construction

 

 



Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express