FDOT District Four - Broward Header Image

Current Construction Lane Closures in North Broward County

- 7.

SR 9/I-95 Mobility Hub at Cypress Creek Road in Fort Lauderdale

Description: Project improvements include: Milling and resurfacing the roadway within project limits, Modifying the median on Cypress Creek Road, adding a 10-foot Shared Use Path (SUP) along Cypress Creek Road, constructing new sidewalks along the northside of NW 59 Court and in each direction of N Andrews Way, upgrading existing lighting to LED fixtures within project limits, installing new mast arms at the intersection of Cypress Creek Road and SR 845/Powerline Road, upgrading pedestrian signals at all signalized intersections within project limits, upgrading signage and pavement markings, installing new landscape within project limits. For more information, please contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Cost/ Completion: $8,148,235/Summer 2025 Traffic Impacts:

Cypress Creek Road from Powerline Road to just west of N Andrews Avenue will have one inside lane closed in each direction daily, as needed, 8:30 a.m. until 4:30 p.m., Monday through Friday, for median construction operations. 8.

Henry E. Kinney Tunnel Improvements and Pedestrian Plaza Project in Fort Lauderdale

Description: Project improvements include rehabilitating the structural, mechanical, electrical, architectural, and life safety components of the Henry E. Kinney Tunnel; milling and resurfacing SR-5/ US-1 from Rio Vista Boulevard to south of the Tunnel; installing Intelligent Transportation Systems (ITS) along SR-5/ US-1; extending the tunnel top to accommodate a pedestrian plaza which will include new fountains, seating facilities, re-designed brick pavers, artificial turf and landscape installation, and reconstructing the intersection of Las Olas Boulevard at SE 6th Avenue. For more information, contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Cost/Completion: $28.4 million / Spring 2024 Traffic Impacts:

US-1 in each direction from I-595 to Broward Boulevard may have up to two lanes closed, daily as needed Monday through Friday.

The pedestrian sidewalk on US-1 will also be closed in association with the operation and pedestrians will be detoured as necessary with signage in place to assist.

US-1 Traffic Configuration:

US-1 will continue to be reduced to one lane in each direction through May 2024.

The northbound tunnel chamber is currently closed, and traffic is shifted to the southbound tunnel chamber, where one lane in each direction will be maintained at all times. This traffic shift is anticipated through Monday morning, April 1 for tunnel rehabilitation operations within the northbound chamber. Signage will be in place to assist motorists.

 The pedestrian sidewalk along US-1 through the tunnel, from SE 6th Street to SE 2nd Street, is closed through Monday morning, March 18 for tunnel rehabilitation operations. Pedestrians are being detoured via SE 3rd Avenue.

Traffic Shift Advanced Notice: Traffic will be shifted to the outside lanes of each tunnel chamber on Monday morning, April 1. The inside lane of US 1, within the tunnel, will be closed. This traffic shift is necessary to safely place rainscreens along the tunnel walls. Signage will be in place to assist motorists.

9.

SR A1A/SE 17th Street Causeway Bridge Painting Project in Fort Lauderdale

Description: The project improvements consist of full removal of the existing bridge paint and repainting of all steel bridge components, cleaning and coating of the movable span piers, traffic and pedestrian concrete railing, and control house. For more information, please contact Interstate Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Cost/ Completion: $4.3 million/Spring 2024 Traffic Impact:

SR A1A/ SE 17th Street Causeway Bridge will have intermittent single lane closures in each direction nightly, as needed, Sunday through Thursday and Saturday, for bridge painting operations. Pedestrian access will be maintained at all times throughout construction.

Westbound Bridge Full Closure Notice: The westbound SR A1A/ SE 17th Street Causeway bridge will be closed intermittently to traffic and pedestrians nightly as needed, 9 p.m. until 7 a.m., Sunday through Thursday, for paint coating operations. Traffic will be detoured via U-turn at Harbor Inlet Drive, eastbound on SR A1A/SE 17th Street Causeway, northbound on SR A1A/Seabreeze Boulevard, westbound on SR 842/ Las Olas Boulevard and southbound on SE 3rd Avenue. Pedestrians will be detoured via Harbor Inlet Drive to the eastbound bridge. Signage will be in place to advise the public. Please click this link to view the detour flyer.

Eastbound Bridge Full Closure Notice: The eastbound SR A1A/ SE 17th Street Causeway bridge will be closed intermittently to traffic and pedestrians nightly as needed, 9 p.m. until 7 a.m., Sunday through Thursday, for paint coating operations. Traffic will be detoured via U-turn at Eisenhower Boulevard, westbound SE 17th Street Causeway, northbound SE 3rd Avenue, and eastbound Las Olas Boulevard to SR A1A/Seabreeze Boulevard. Pedestrians will be detoured via Eisenhower Boulevard to the westbound bridge. Signage will be in place to advise the public. Please click this link to view the detour flyer.

Crews will not have consecutive bridge closures on the same night.

10.

SR A1A Advanced Transportation Management System (ATMS) Implementation Project in Fort Lauderdale

Description: The project improvements include upgrading and installing a new fiber optic network; installing Intelligent Transportation System (ITS) devices including Closed-Circuit Television Cameras (CCTV) controlled by wireless network devices; installing Bluetooth travel time devices along the corridor; installing two Arterial Dynamic Messaging Signs (ADMS); upgrading Traffic Signal Vehicle Detection Systems along the corridor; and removing and reinstalling existing pavers where impacted by construction. Cost/Completion: $9,138,494 / Spring 2025 Traffic Impact:

SR 838/Sunrise Boulevard from SR 5/US 1 to SR A1A/Seabreeze Boulevard may have one lane close in each direction nightly, as needed, from 9 p.m. until 7:30 a.m.

11.

SR 25/US 27 Shoulder Widening Project in Weston

Description: Project Improvements include widening the shoulders along US 27, installing signage, pavement marking, and illuminated raised pavement markings, removing and replacing guardrail, as needed, upgrading Intelligent Transportation System (ITS) components. For more information, please contact I-95 Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Cost/Completion: $15,781,904 / Spring 2024 Traffic Impact:

Northbound US-27, from I-75 to the Broward and Palm Beach County Line, may have one lane and the shoulder closed daily, as needed.

Southbound US-27, from the Palm Beach County Line to I-75 in Broward, may have one lane and the shoulder closed daily, as needed.

12.

SR

817/University Drive from SR 84 To NW 1st Street Improvements Project in Plantation

Description: Project improvements include widening the roadway to accommodate bicycle lanes in each direction; upgrading curb ramps, signage, and pavement markings; constructing bus shelters at existing bus stop locations; upgrading pedestrian signals with countdown timers at Peters Road, the Fountains Entrance, Federated Road, and SR 842/Broward Boulevard; and removing and replacing light poles impacted by widening operations. For more information, please contact Community Assistant Community Outreach Specialist Alejandra Pozo at (561) 690-1807 or apozo@corradino.com. Cost/Completion: $8,895,417 / Spring 2024 Traffic Impacts:

University Drive from just south of I-595 to Broward Boulevard may have one lane closed in each direction daily, as needed, 8 a.m. until 4 p.m., Monday through Friday for roadway widening operations.

Eastbound Broward Boulevard to University Drive may have one turn lane closed daily, as needed, 8 a.m. until 4 p.m., Monday through Friday for roadway widening operations.

University Drive from just south of I-595 to NW 1 Street may have two lanes closed in each direction nightly, as needed, 10 p.m. until 6 a.m., Sunday through Thursday for signalization activities. 13.

SR 838/Sunrise Boulevard from NW 34th Avenue to SR 845/Powerline Road Lighting Improvements Project in Fort Lauderdale

Description: Project improvements consist of upgrading existing lighting to light-emitting diode (LED) luminaires and installing new light posts to enhance illumination along Sunrise Boulevard between NW 34th Avenue and SR 845/ Powerline Road. For more information, please contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Cost/Construction Start: $798,900/Early 2024 Traffic Impacts:

Westbound Sunrise Boulevard from NW 34th Avenue to Powerline Road will have the outside lane closed in segments daily, as needed 9 a.m. until 3 p.m., Monday through Thursday for light pole foundation installation operations. 14. SR 7/US 441 Mobility Improvements Project along Prospect Road in Fort Lauderdale, North Lauderdale, and Tamarac Description: Project improvements include widening the roadway to accommodate buffered bicycle lanes in both directions; constructing new sidewalks along the south side of Prospect Road from SR 7/US-441 to NW 31st Avenue and along both sides of Prospect Road from NW 31st Avenue to SR-870/Commercial Boulevard; upgrading signage and pavement markings; and milling and resurfacing within the project limits. For more information, please contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Cost/Completion: $6.7 million/ Final Accepted: March 15, 2024 15.

SR 817/University Drive in Coral Springs Mobility Improvement Project in Coral Springs

Description: Project improvements consist of widening to accommodate two additional travel lanes and to increase the bike lanes from 4-feet to 7-feet from NW 40th Street to SR-869/Sawgrass Expressway, relocating existing 6-foot sidewalk from NW 40th Street to SR-869/Sawgrass Express, relocating impacted drainage structures, regarding swales to ensure proper drainage flow, upgrading traffic and pedestrian signals at NW 40th Street and Westview Drive, installation of 77 light poles along the project corridor, milling and resurfacing within the project limits, and upgrading curb ramps, signing, and pavement markings. For more information, please contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Cost/Completion: $13,650,945 / Late 2024 Traffic Report:

University Drive from Wiles Road to Westview Drive will have one lane closed nightly, as needed, 10 p.m. until 6 a.m., Monday through Friday, for paving operations.

University Drive from Sample Road to NW 40th Street will have one lane closed daily, as needed, 9 a.m. until 4 p.m., Monday through Friday for new signal installation operations. 16.

SR 842/Broward Boulevard Resurfacing, Restoration, and Rehabilitation (RRR) Project in Plantation

Description: Project improvements include milling and resurfacing the pavement throughout the project limits, reconstructing sidewalks, curb ramps, and upgrading detectable warning surfaces, upgrading traffic signalization, upgrading pedestrian signals with countdown timers and LED lighting at six intersections, and upgrading signing and pavement markings. For more information, please contact Assistant Community Outreach Specialist Alejandra Pozo at (561) 690-1807 or apozo@corradino.com. Cost/Completion: $4.14 million / Early 2024 Traffic Report:

Broward Boulevard from University Drive to East Acre Drive will have intermittent segments closed in each direction daily, as needed, 9 a.m. until 3:30 p.m., Monday through Friday. 17.

SR 842/Broward Boulevard Resurfacing Project in Plantation, Fort Lauderdale and Lauderhill

Description: Project improvements include upgrading pedestrian signals at all signalized intersections within the project limits, installing 39 light poles and upgrading existing lighting with LED fixtures between US 441/SR 7 and W 27th Avenue, removing decorative paver crosswalks, extending median left turn lanes to increase vehicle capacity at various locations, milling and resurfacing the roadway, and upgrading signing and pavement markings. For more information, please contact Assistant Community Outreach Specialist Angel Breedlove at (786) 494-6211 or abreedlove@corradino.com. Cost/Completion: $7,262,972 / Fall 2024 Traffic Impact:

Broward Boulevard from west of NW 42nd Avenue to SW 22nd Avenue will have one lane closed intermittently in each direction as needed, 9 a.m. until 3:30 p.m., and 8:30 p.m. until 7 a.m.

Full Closure Notice: NW 34th Avenue at SR 842/Broward Boulevard will be closed from 10 p.m., Friday, March 15, to 6 a.m., Monday, March 18, for crosswalk construction. NW 34th Avenue traffic will be detoured via NW 4th Street, Martin Luther King Jr. Avenue/NW 31st Avenue, and SR 842/ Broward Boulevard. SR 842/Broward Boulevard traffic will be detoured via Martin Luther King Jr. Avenue/NW 31st Avenue, NW 4th Street, and NW 34th Avenue. Posted signs will assist motorists. SR 842/Broward Boulevard at NW 34th Avenue will have two lanes closed in either direction at any one time for crosswalk construction along SR 842/Broward Boulevard. Posted signs will assist motorists. Please click this link to view the detour flyer.

Advanced Notice: SR 842/Broward Boulevard at NW 31st Avenue will have two lanes closed in either direction at any one time for crosswalk construction operations beginning 10 p.m., Friday, March 22, through 6 a.m., Monday, March 25. 18.

NW 29th Street Mobility Improvement Project

in Wilton Manors Description: Project improvements include widening the roadway to accommodate 4-foot bicycle lanes in each direction, constructing new sidewalks along the south side of the corridor, upgrading pedestrian crosswalks to countdown timers at N. Andrews Avenue, milling and resurfacing the roadway within the project limits, replacing the decorative stamped concrete at the intersections of NW 7th Avenue, NW 6th Avenue, and NW 3rd Avenue. For more information, please contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Cost/Completion: $2,323,590 / Spring 2024 Traffic Impacts:

Full Closure: NW 29th Street between Andrews Ave and NW 3rd Avenue will be fully closed through 3:30 p.m., Sunday, March 31, for drainage operations and the installation of the decorative stamped concrete. Traffic will be detoured via SR 845/Powerline Road/NW 9th Avenue, NW 16th Street, and SR 811/N. Andrews Avenue. Access to local road and residential properties will be maintained always. Please click this link to view the detour flyer. 19.

Rail Traffic Monitoring Improvements Project at five State Road Crossings in Fort Lauderdale, Oakland Park, Hollywood, and Hallandale Beach

Description: Project improvements include installing train detection systems at the Florida East Coast (FEC) Railroad crossings located at the SR 816/Oakland Park Boulevard, SR 838/Sunrise Boulevard, SR 84/Marina Mile Boulevard from to SR 5/US 1, SR 824/Pembroke Road, and SR 858/Hallandale Beach Boulevard intersections. Installing fiber optic cable, overhead dynamic message signs and other Intelligent Transportation Systems (ITS) devices on SR 84 between SR 9/I-95 and SR 5/US 1. Additional improvements along SR 84 will include installing of: microwave vehicle detection system (MVDS) in the vicinity of the FEC railway that will be connected to existing ITS cabinets at each of these corridors; new FDOT fiber optic cable from SR 9/I-95 to SR 5/US 1; arterial dynamic message signs (ADMS), CCTV cameras, and Bluetooth devices. For more information, please contact Assistant Community Outreach Specialist Alejandra Pozo at (561) 690-1807 or apozo@corradino.com. Cost/Completion: $3 million / Spring 2024 Traffic Impacts:

SR 84/Marina Mile Boulevard from I-95 to US 1 will have one lane closed in each direction daily, as needed,10 a.m. until 4 p.m., for fiber optic cable installation operations.

Northbound SE 4th Avenue at SR 84/Marina Mile Boulevard will have one lane closed daily as needed, 10 a.m. until 4 p.m., Monday through Friday, for drainage and road widening operations. 20.

Loxahatchee Road Mobility Improvements Project in Parkland

Description: Project improvements include widening the road to accommodate bike lanes, creating a continuous sidewalk on the south side of the road, constructing roundabouts at Nob Hill Road, University Drive, and Parkside Drive, adding an additional eastbound left turn lane onto SR 7/US 441, milling and resurfacing the roadway, and upgrading signage and pavement markings. For more information, please contact Community Outreach Specialist Daniela Silva at (786) 441-3088 or msilva@corradino.com. Cost/Completion: $33,480,584 / Early 2027 Traffic Impacts:

Full closure: Loxahatchee Road from SR 817/N University Drive to Parkside Drive will be closed around-the-clock through Fall 2024. Traffic will be detoured via SR 817/N University Drive, Holmberg Road, and Parkside Drive. Access to local roads and residential properties between the work zone and Parkside Drive will be maintained. Please click this link to view the detour flyer. 21.

SR 5/US 1/Federal Highway Resurfacing Project in Pompano Beach and Fort Lauderdale

Description: Project improvements include milling and resurfacing the roadway, modifying pavement markings along SR 5/US 1/Federal Highway to accommodate 4-foot bicycle lanes in each direction, upgrading pedestrian signals with countdown timers, LED lighting at various intersections, and upgrading signage, pavements markings, sidewalks, and curb ramps. For more information, please contact Assistant Community Outreach Specialist Angel Breedlove at (786) 494-6211 or abreedlove@corradino.com. Cost/Completion: $5,869,408 / Summer 2024 Traffic Impacts:

SR 5/US1 will have one lane intermittently closed in each direction nightly, as needed, 9 p.m. until 7 a.m., Monday through Friday.

SR 5/US1 will have one lane intermittently closed in each direction daily, as needed, 9:30 a.m. until 1:30 p.m., Monday through Friday

Intersecting side streets between Commercial Boulevard and SE 7th Street will have one lane intermittently closed in each direction daily, as needed, 9:30 a.m. until 3:30 p.m., Monday through Friday. 22. SR 5/US 1/Federal Highway Improvements Project in Oakland Park and Fort Lauderdale Description: Project improvements include milling and resurfacing the roadway, modifying pavement markings along SR 5/US 1/Federal Highway to accommodate 4-foot bicycle lanes in each direction, extending the northbound left-turn lane on SR 5/US 1/Federal Highway at NE 26th Street to increase vehicle storage capacity, upgrading existing signalization and lighting with LED fixtures at various locations, upgrading signage, pavement markings, sidewalks, and curb ramps. For more information, please contact Assistant Community Outreach Specialist Angel Breedlove at (786) 494-6211 or abreedlove@corradino.com. Cost/Completion: $8,153,789 / Fall 2024 Traffic Impacts:

SR 5/US1 will have one lane intermittently closed in each direction nightly, as needed, 9 p.m. until 7 a.m., Monday through Friday.

Intersecting side streets between Sunrise Boulevard and Oakland Park Boulevard will have one lane intermittently closed in each direction daily, as needed, 9:30 a.m. until 3:30 p.m., Monday through Friday.

NORTH BROWARD: (Coconut Creek, Coral Springs, Deerfield Beach, Fort Lauderdale, Hillsboro Beach, Lauderdale Lakes, Lauderdale-By-The-Sea, Lauderhill, Lazy Lake, Lighthouse Point, Margate, North Lauderdale, Oakland Park, Parkland, Plantation, Pompano Beach, Sea Ranch Lakes, Sunrise, Tamarac, Wilton Manors)

Traffic Impact: Westbound Commercial Boulevard at the intersection of Northeast 13 Avenue, in Fort Lauderdale, 9 p.m. – 4 a.m., Sunday through Thursday, Monday, Mar. 11 through Tuesday, Apr. 30, 2 of 3 lanes closed, for force main installation. For more information, please contact Anthony Britten 954-384-1675.

Traffic Impact: Southbound North Federal Highway at 1555 North Federal Highway, in Fort Lauderdale, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Feb. 26 through Friday, Mar. 08, 1 of 3 lanes closed, for water and sewer maintenance. For more information, please contact Heidi Jarquin 305-752-7742.

Traffic Impact: Northbound and Southbound North Ocean Boulevard at 900 North Ocean Boulevard, in Pompano Beach, 9 p.m. until 4 a.m., Sunday through Thursday, Monday, Feb. 26 through Tuesday, Mar. 26, 1 of 1 lane closed, for piping installation. For more information, please contact Shawn Alava 786-631-2949.

Traffic Impact: Northbound and Southbound Powerline Road between Northwest 36 Street and Prospect Road, in Fort Lauderdale, 9 p.m. until 4 a.m., Sunday through Thursday, Monday, Dec. 04 extended through Thursday, Mar. 28, 1 of 2 lanes closed, for water valve replace and installations. For more information, please contact Bobby Bucci 954-931-2712.

Traffic Impact: Westbound Sistrunk Boulevard between Northwest 20 Avenue and Northwest 21 Terrace, in Fort Lauderdale, 9 a.m. until 4 p.m., Monday through Friday, Monday, Jun. 06 extended through Friday, Jun. 14, 1 of 2 lanes closed, for handholes, underground boring and fiber installation. For more information, please contact Kyle Alsop 561-490-4335.

Traffic Impact: Westbound and Eastbound East State Road 84 between Southeast 4 Avenue and Miami Road, in Fort Lauderdale, 9 a.m. until 4 p.m., Monday through Friday, Monday, Feb. 26 through Tuesday, Apr. 30, 1 of 3 lanes closed, for median modification, widening, handicap ramp, signalization, milling and resurfacing. For more information, please contact Elliot Eichel 954-680-8005.

Traffic Impact: Northbound and Southbound US Dixie Highway between Oakland Park Boulevard and Prospect Road, in Oakland Park, 9:30 a.m. – 3:30 p.m., Monday through Friday, Tuesday, Feb. 27 through Friday, Mar. 29, 1 of 2 lanes closed, for soil boring installation. For more information, please contact Juan Valencia 786-436-6811.

Traffic Impact: Westbound Broward Boulevard between Northwest 33 Terrace and Southwest 31 avenue, in Fort Lauderdale, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Feb. 26 through Friday, Apr. 26, 1 of 3 lanes closed, for directional boring, antenna, utility pole installation. For more information, please contact Caylin Pacheco 786-567-3734.

Traffic Impact: Westbound Hillsboro Boulevard between Powerline Road and Northwest 45 Avenue, in Deerfield Beach, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Jun. 10 extended through Friday, Apr. 26, 1 of 3 lanes closed, for hand hole and underground installation. For more information, please contact Carlos Gonzalez 954-382-5186.

Traffic Impact: Westbound Griffin Road between Southwest 38 Avenue and Southwest 44 Avenue, in Fort Lauderdale, 9 a.m. – 3:30 p.m., Monday through Friday, Monday, May 09 extended through Friday, Mar. 29, 1 of 3 lane closed, for handholes and fiber installations. For more information, please contact Kyle Alsop 561-490-4335.

Traffic Impact: Westbound Pines Boulevard between North 72 Avenue and University Drive, in Pembroke Pines, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Nov. 06 extended through Friday, Mar. 29, 1 of 3 lanes closed, for slice box, underground boring and cable installation. For more information, please contact David Whitehead 954-415-0858.

Traffic Impact: Northbound State Road 7 between Northwest 41 Street and Northwest 62 Street, in North Lauderdale, Lauderdale Lakes and Tamarac, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, May 15 extended through Friday, Mar. 29, 1 of 3 lanes closed, for handholes, underground directional boring and fiber installation. For more information, please contact Richard Acosta 305-345-2246.

Traffic Impact: Northbound Southwest 21 Terrace at the intersection of Southwest 1 Street, in Fort Lauderdale, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Jan. 22 through Friday, Mar. 22, 1 of 1 lane closed, for utility pole installation. For more information, please contact Daylin Pacheco 786-567-3734.

Traffic Impact: Southbound Seabreeze Boulevard South to Harbour Drive, in Fort Lauderdale, 9 a.m.- 3:30 p.m., Monday through Friday, Tuesday, Jan. 03 extended through Monday, Jun. 30, 2024, 1 of 2 lanes closed, for sidewalk maintenance. For more information, please contact Camila Vayas 305-573-8030.

Traffic Impact: Westbound Griffin Road between Southwest 38 Avenue and Southwest 44 Avenue, in Fort Lauderdale, 9 a.m. – 3:30 p.m., Monday through Friday, Monday, May 09 extended through Wednesday, Jan. 31, 2024, 1 of 3 lanes closed, for handholes and fiber installations. For more information, please contact Kyle Alsop 561-490-4335.

Traffic Impact: Northbound State Road 7 between Northwest 49 Street through Northwest 62 Street, in Fort Lauderdale, 9 a.m. until 4 p.m., Monday through Friday, Monday, Jul. 17 extended through Friday, Apr. 12, 1 of 3 lanes closed, for handholes and facilities installation. For more information, please contact Allen Martin 770-527-9775.

Traffic Impact: Northbound State Road 7 between Northwest 16 Street and West Oakland Park Boulevard, in Fort Lauderdale, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, May 02 extended through Friday, Mar. 29, 1 of 3 lanes closed, for directional boring and fiber installation. For more information, please contact Kyle Alsop 561-490-4335.

Traffic Impact: Eastbound and Westbound West Oakland Park Boulevard between Northwest 23 Terrace and Northwest 18 Avenue, in Oakland Park, 9 a.m. until 3:30 p.m., Monday through Friday, Wednesday, Dec. 08 extended through Friday, Mar. 29, 1 of 3 lanes closed, for hand holes, underground boring and fiber installation. For more information, please contact Erwin Mosqueda 954-789-7600.

Traffic Impact: Northbound and Southbound South Federal Highway between Northeast 48 Street and Southeast 12 Street, in Fort Lauderdale, 9 a.m. - 3:30 p.m., Monday through Friday, Wednesday, Feb. 09 extended through Friday, Mar. 29, 1 of 3 lanes closed, for lighting improvements. For more information, please contact Anna Tupitsyna 954-551-5130.

Traffic Impact: Northbound and Southbound North Ocean Drive between East Hillsboro Boulevard and Northeast 7 Street, in Deerfield Beach, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Jul. 24 extended through Friday, Mar. 29, 1 of 1 lanes closed as needed, for directional boring installation. For more information, please contact David Whitehead 954-415-0858.

Traffic Impact: Northbound Seabreeze Boulevard between Harbor Beach Parkway and Southeast 5 Street, in Fort Lauderdale, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Jan. 03 extended through Friday, Mar. 29, 1 of 2 lanes closed as needed, for hand hole installation and facilities work. For more information, please contact Erwin Mosqueda 594-789-7600.

Traffic Impact: Southbound State Road 7 between Northwest 26 Street and Northwest 24 Street, in Lauderhill, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Jan. 08 through Friday, Mar. 08, 1 of 3 lanes closed, for communication equipment, wireless antenna and pole installation. For more information, please contact Daylin Pacheco 786-567-3734.

Traffic Impact: Westbound and Eastbound Oakland Park Boulevard just West of I-95 over train rail crossings, in Oakland Park, 9 p.m. until 6 a.m., Sunday through Thursday, 3 of 3 lanes closed, for signal, cantilever safety upgrades. For more information, please contact Roosevelt Bynes III 954-321-8205.

Traffic Impact: Eastbound West Sunrise Boulevard and Southbound North University Drive, in Plantation, 9 a.m. -3:30 p.m., Monday through Friday, Monday, Jun. 27 extended through Tuesday, Apr. 30, 1 of 3 lanes closed, for directional borings, hand holes and fiber optic cables installations. For more information, please contact David Weitzman 305-431-7689.

Traffic Impact: Eastbound State Road 84 between Southwest 130 Avenue and Southwest 117 Avenue, in Davie, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, May 09 extended through Tuesday, Apr. 30, 1 of 3 lanes closed, for directional borings, hand holes and fiber optic cables installations. For more information, please contact Maria Pena 954-937-5305.

Traffic Impact: Eastbound West Broward Boulevard crossing over Turnpike, in Fort Lauderdale, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Apr. 18 extended through Tuesday, Apr. 30, 2 of 4 lanes closed, for directional borings, handholes and conduit installation. For more information, please contact Ali Garces 954-937-5305.

Traffic Impact: Northbound Powerline Road between Southwest 2 Court and Southwest 18 Street, in Deerfield Beach, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Oct. 30 extended through Friday, Jun. 07, 1 of 2 lanes closed, for fiber development and grid modernization. For more information, please contact Kyle Alsop 561-490-4335.

Traffic Impact: Westbound and Eastbound Northwest 41 Street at the intersection of Northbound North State Road 7, in Lauderhill, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, May 08 extended through Friday, Mar. 08, 1 of 2 lane closed, for maintenance and installation. For more information, please contact Bobby Bucci 954-931-2712.

Traffic Impact: Eastbound West Commercial Boulevard just East of State Road 7, in Fort Lauderdale, 9:30 a.m. – 4 p.m., Monday through Friday, Monday, Feb. 12 through Friday, Apr. 26, 1 of 3 lanes closed, for utility pole, antennas, equipment cabinet, electrical and fiber installation. For more information, please contact John Criscione 732-410-1708.

Traffic Impact: Northbound and Southbound US Highway A1A between Sunset Lane and Southeast 7 Street, in Pompano Beach, 9 a.m. – 3:30 p.m., Monday through Friday, Monday, Feb. 12 through Thursday, Jun. 13, 1 of 1 lanes closed as needed, for sidewalk, bus shelter, landscape PED crossing, roadway irrigation, milling resurfacing and landscape median installation. For more information, please contact Urma Charlemagne 561-418-0598.

Traffic Impact: Westbound Dave Boulevard between Southwest 34 Avenue and Southwest 37 Avenue, in Fort Lauderdale, 9 a.m. – 3:30 p.m., Monday through Friday, Tuesday, Feb. 13 through Friday, Apr. 26, 1 of 2 lanes closed, for directional boring installation. For more information, please contact Jorge Galindo 954-235-8319.

Traffic Impact: Northbound and Southbound North Ocean Drive between Northeast 11 Street and Northeast 12 Street, in Pompano Beach, 9 p.m. – 4 a.m., Sunday through Thursday, Monday, Nov. 08 extended through Monday, Mar. 18, 1 of 2 lanes closed, for new water and sewer underground excavation. For more information, please contact Shawn Alava 786-631-2949.

Traffic Impact: Eastbound Broward Boulevard between Southwest 29 Terrace and Southwest 27 Terrace, in Fort Lauderdale, 9 am - 3:30 pm, Monday through Friday, Monday, Feb. 19 through Friday, Apr. 19, 1 of 3 lanes closed, for pole and antenna installation. For more information, please contact Daylin Pacheco 786-567-3734.

Traffic Impact: Northbound North Federal Highway between Sample Road and Northeast 44 Street, in Pompano Beach, 9 p.m. until 3 a.m., Monday through Friday, Monday, Feb. 19 through Friday, Mar. 29, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Luis Egozcue 786-546-1138.

Traffic Impact: Northbound and Southbound North Ocean Boulevard at 900 North Ocean Boulevard, in Pompano Beach, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Nov. 13 extended through Monday, Mar. 18, 1 of 1 lane closed, for piping installation. For more information, please contact Shawn Alava 786-631-2949.

Traffic Impact: Westbound Stirling Road between Anglers Avenue and North Park Road, in Fort Lauderdale, 9:30 a.m. -3:30 p.m., Monday through Friday, Monday, Jan. 31 extended through Friday, May 17, 1 of 3 lanes closed, for handholes, fiber and underground boring installation. For more information, please contact Erwin Mosqueda 954-551-5130.

Traffic Impact: Northbound and Southbound South Powerline Road between Southwest 15 Street and Southwest 11 Street, in Deerfield Beach, 9 a.m. - 3:30 p.m., Monday through Friday, Wednesday, Feb. 21 through Friday, Mar. 22, 1 of 3 lanes closed, for water directional boring and conduit installation. For more information, please contact Ernesto Millan 786-236-8597.

Traffic Impact: Northbound Northeast 4 Avenue between Northeast 7 Street and East Sunrise Boulevard, in Fort Lauderdale, 9 a.m. - 3:30 p.m., Monday through Friday, Monday, Feb. 26 through Friday, Apr. 26, 1 of 2 lanes closed, for utility pole, antenna, and mounting installation. For more information, please contact Daylin Pacheco 786-567-3734.

Traffic Impact: Westbound and Eastbound West Atlantic Boulevard at intersection of Lyons Road, in Pompano Beach, 9 p.m. until 4 a.m., Sunday through Thursday, Sunday, Mar. 03 through Monday, Mar. 11, 2 of 3 lanes closed, for bridge rehabilitation. For more information, please contact Lazaro Arzuaga 786-560-1177.

Traffic Impact: Southbound and Northbound South Federal Highway between Southeast 13 Court and Southeast 10 Street, in Deerfield Beach, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, Mar. 04 through Monday, May 06, 1 of 3 lanes closed, for directional boring, conduit, handhole installation. For more information, please contact Urma Charlemagne 561-418-0598.

Traffic Impact: Westbound and Eastbound Northwest 41 Street at the intersection of Northbound North State Road 7, in Lauderhill, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, May 08 extended through Wednesday, Jul. 31, 1 of 2 lane closed, for maintenance and installation. For more information, please contact Bobby Bucci 954-931-2712.

Traffic Impact: Southbound State Road 7 at 541 State Road 7, in Margate, 9 a.m. – 3:30 p.m., Monday through Friday, Monday, Feb. 12 extended through Friday, Mar. 08, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Eddy Perez 954-558-4290.

Traffic Impact: Westbound West Sample Road between Northwest 5 Avenue and North Powerline Road, in Pompano Beach/Deerfield Beach, 9 a.m. until 4 p.m., Monday through Friday, Monday, Mar. 27 extended through Friday, May 17, 1 of 3 lanes closed, for directional boring and trench installation. For more information, please contact Richard Acosta 305-345-2246.

Traffic Impact: Northbound State Road 7 just 500’ ft North and South of intersection of Lauderhill Avenue of the Arts, in Lauderdale Lakes, 9 a.m. – 3:30 p.m., Monday through Friday, Monday, Mar. 04 through Friday, Mar. 29, 1 of 3 lanes closed, for directional drilling and conduit installation. For more information, please contact Eddy Perez 954-558-2363.

Traffic Impact: Northbound North Federal Highway between Northeast 37 Street and Northeast 37 Drive, in Fort Lauderdale, 9 a.m. until 4 p.m., Monday through Friday, Monday, Mar. 04 through Friday, Mar. 29, 1 of 2 lanes closed, for water valve replacement. For more information, please contact Anthony Britten 954-384-1675.

Please click on a link below to view lane closures in other areas of Broward County:



Interstate Broward County ClosuresInterstate Broward County Closures

I-95 Express Broward County Closures95 Express Broward County Closures

Northeast Broward County ClosuresNortheast Broward County Closures

Northwest Broward County ClosuresNorthwest Broward County Closures

Southeast Broward County ClosuresSoutheast Broward County Closures

Southwest Broward County ClosuresSouthwest Broward County Closures

Broward County Maintenance and Permit ClosuresBroward County Maintenance and Permit Closures

Broward County Lane ClosuresClick here to download PDF versions of the FDOT and Broward County lane closures

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express