official project website: www.sw10street.com
Financial Number: 439891-1-22-02
Project Length: 3 miles
Project Limits: Florida’s Turnpike/Sawgrass Expressway to west of I-95
Start Date: Design-Build funding starting in FY 2023
Anticipated Completion Date: 2027/28
Estimated Construction Cost: $325 M with Powerline Road Ramps Alternative; $229 M without Powerline Road Ramps Alternative
Scope of Work:
- Add four-lane connector road (includes center barrier wall, outside barrier wall, and full width paved shoulders)
- Add 12-foot wide shared use path on the southside of local SW 10th Street
- Enhance crosswalks at Powerline Road and Military Trail
Benefits of the Build Alternatives:
- Reduces Congestion
- With Powerline Road Ramps: Reduced local traffic peak hour 2040 design year volumes below current traffic level by -73% in the am and -52% in the pm
- Without Powerline Road Ramps: Reduces local traffic peak hour 2040 design year volumes below current traffic level by -40% in the am and -20% in the pm
- Promotes Regional Connectivity:
- Connects limited access facilities: I-95, Sawgrass, and Turnpike via a high-speed corridor
- Improves Emergency Response Times and Evacuation Operations
- Improves Pedestrian and Bicycle Connectivity: 12-foot wide shared use path throughout the corridor
Contact Information:
SW 10th Street Connector PD&E Study
|