Treasure Coast Header Image

CR 619/82nd Avenue from 26th Street to CR 510/Wabasso Road

Financial Number: 230879-2-52-01 & 230879-3-52-01

Project Length: 7.046 miles

Project Limits: CR 619/82nd Avenue from 26th Street to CR 510/Wabasso Road

County: Indian River

Start Date: TBD

Completion Date: TBD

Contractor: TBD

Estimated Construction Cost:

  • North Project: $10.6 million
  • South Project: $29.3 million

Scope of Work:
Construct 2 lane - 2 way roadway with 5 feet paved shoulders from 26th Street to CR 510 through existing dirt road, pastures and citrus grove. Construct 3 box culverts and 1 bridge to replace existing wooden pile bridges. The proposed drainage conveying system will consist of a series of swales along both the east and west sides of the new 82nd Avenue roadway alignment. The swales will convey runoff to the proposed wet detention pond within the basin. Offsite runoff will only include the runoff from the 30 foot berm area between Lateral C Canal and proposed swale on the west side of the roadway. The design of the storm water management facilities is to address both water quality treatment and water quantity attenuation. The ponds will overflow directly into Lateral C Canal. The existing flow control structures located in the existing sub canals will be relocated to the east of the proposed roadway R/W. Existing power poles at 69th Street are to be relocated.

Documents:

PDF Icon82nd Ave - 2 Mile Roll Plot

PDF Icon82nd Ave - 5 Mile Roll Plot

PDF Icon82nd Avenue Public Meeting Presentation

PDF Icon82nd Avenue Public Meeting Flyer

Contact Information:

 
 
 

Project Photos

Click to view enlarged version/details





Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone