Financial Number: 444336-1-52-01
Project Length: 1.42 miles
Project Limits: SR 9/I-95 at St. Lucie West Boulevard
Virtual Public Workshop: No Workshop will be held.
Projected Letting: January 2025
Anticipated Construction Start Date: Spring 2025
Anticipated Construction Completion Date: Fall/Winter 2025
Estimated Construction Cost: $892,176.00
Scope of Work:
- Landscape improvements primarily addressing the I-95 and St. Lucie West Boulevard interchange with additional improvements being made to the St. Lucie West Boulevard medians.
- New landscaping and irrigation will be provided to supplement the existing trees, palms, and shrubs.
- Project intent is to restore impacts from roadway construction on the interchange landscaping.
Construction Impacts:
- Work will be done in phases to reduce the impact on traffic.
- No lane closures or detours along I-95 or the interchange ramps are anticipated.
- Temporary lane closures adjacent to the St. Lucie West Boulevard medians will be required.
- No lane closures will be allowed during special events.
Documents:
St Lucie West_Summary of Analysis.pdf
44433615201_Flyer.pdf
St Lucie West_Rendering.pdf
Updated Project Flyer
Point of Contact:
Para información y preguntas en Español, por favor llame al (954) 777-4302.
|