Financial Number: 4432645-2-52-01
Project Length: 0.019 miles
Project Limits: SR 5/US-1 at Morningside Drive intersection in Martin County
Online Public Information Meeting: Tuesday, January 18, 2022; Beginning at 5:00 p.m.
Link to registration page: www.tinyurl.com/US-1Morningside
In-Person Public Information Meeting: Wednesday, January 19, 2022; 5:00 p.m. – 7:00 p.m. (Open House) at the Robert Morgade Library located at 5851 SE Community Drive, Stuart, FL 34997. The latest social distancing guidelines will be followed.
Projected Letting: February 2020
Start Date: Spring 2022
Completion Date: Summer 2022
Estimated Construction Cost: $40,000
Scope of Work:
- Reconfigure existing full median opening to a directional median by constructing a raised median separator.
Construction Impacts:
- Daytime, temporary, single lane closures will occur to construct the raised median. The left turn lanes will also be temporarily closed to fully construct the median improvements. NB traffic needing to access Morningside Dr. will be required to complete a U-turn.
- Traffic exiting Morningside Drive that desires to turn north on US-1 will be required to initially turn south and seek the left turn lane at Mariner Sands Drive to complete the required U-turn (SB-to-NB) movement.