Financial Number: 433685-1-52-01
Project Limits: Okeechobee Road/SR 70 and Midway Road/CR 712 intersection
Start Date: October 5, 2020
Completion Date: March 5, 2021
Contractor: Wiretek Solutions, LLC
Estimated Construction Cost: $255,430
Scope of Work: The improvements under this contract consist of installing highway lighting at the Okeechobee Road/SR 70 and Midway Road/CR 712 intersection.