Financial Number:
427012-1-32-01
Project Length: 3.23 miles
Project Limits: Flamingo Road from north of Griffin Road to south of State Road 84
Start Date: November 23, 2015
Completion Date: December 22, 2016
Contractor: Community Asphalt, Corp.
Estimated Construction Cost: $4.14 million
Scope of Work
Project improvements include adding a 5-foot sidewalk along the west side of Flamingo Road, upgrading pedestrian ramps and sidewalks to meet current ADA standards, adding pedestrian poles at SW 36th Court, removing old asphalt and resurfacing Flamingo Road within project limits, upgrading existing guardrail to meet current safety standards, signing and pavement marking improvements. Other improvements include installing 2 overhead signs to guide motorists towards major thoroughfares such as I-75, I-595, I-95, Griffin Road, and State Road 84, drainage improvements at SW 26th Street, and widening Flamingo Road at specified areas to accommodate bus bays and continuous bicycle lanes.
|