Financial Number: 447672-1-52-01
Project Length: 0.885 miles
Project Limits: State Road (SR) 844/NE 14th Street from SR 5/US 1 to west of SR A1A
Start Date: Spring 2025
Completion Date: Winter 2025
Estimated Construction Cost: $1.9 million
Scope of Work:
- Repaving the existing roadway
- Upgrading non-compliant sidewalk ramps
- Upgrading pedestrian signal features and pedestrian lighting at 2 signalized
- Completing an existing gap in the eastbound bike lane network, enhancing safety for bicyclists
Construction Impacts:
- Work will be done in phases to reduce the inconvenience to the community
- Lane closures will occur one lane at a time during non-peak hours to minimize impacts on traffic
- No full roadway closures are anticipated
- Access to all properties will be maintained at all times
Documents:
Typical Right Turn.pdf
Meeting Invitation and Project Presentation
Point of Contact:
Project Location Map
|