Financial Number: 439939-1-52-01, 439940-1-52-01, 440143-1-52-01 & 440143-2-52-01
Project Length: 14.8 miles
Project Limits: SR 25/US 27 from the I-75 Interchange to the Broward/Palm Beach County Line
Virtual Public Workshop: No public workshop is scheduled for this project.
Projected Letting: May 2021
Start Date: Summer 2021
Completion Date: Spring 2023
Estimated Construction Cost: $22.9 M
Scope of Work:
- Construction of auxiliary lanes at the entrance/exits to boat ramp areas
- Installation of shoulder rumble strips and internally illuminated raised pavement markings (IIRPM’s).
- Shoulder widening to provide 10 foot wide paved roadside and median shoulders to provide a stable and clear space for emergency refuge by vehicles.
- Intelligent Transportation System (ITS) upgrades to interconnection and power supply for improved communications and power supply to existing devices.
Construction Impacts:
- Construction will be done in phases to reduce the effects of construction on the community.
- Temporary lane closures will occur during non‐ peak hours and will be limited to a maximum length of 3 miles.
Contact Information:
Documents:
SR‐25/US‐27 Safety Project Flyer
|