Financial Number: 449257-1-52-01
Project Length: 0.207 mile
Project Limits: East Las Olas Boulevard over Intracoastal Waterway
Public Meeting:
Projected Letting: Spring 2025
Anticipated Start Date: Spring 2026
Anticipated Completion Date: Spring 2027
Estimated Construction Cost: $12 M
Scope of Work:
- Replace old deck with new solid surface aluminum deck
- Paint the movable bridge deck and fascia elements
- Replace the mechanical span locks which connect the two halves of the movable bridge deck when the bridge is in the "down" position
- Replace important electrical components and wiring
- Replace the mechanical span locks which connect the two halves of the movable bridge deck when the bridge is in the "down" position
- Replace the existing navigation/marine fenders in the waterway, including replacement of the timber piles and support beams
- Renovate the bridge tender house
- Minor repaving of the roadway at ends of the bridge and restore traffic monitorng site
Construction Impacts:
- Full bridge closures will occur during certain phases, and detours will be provided utilizing Sunrise Boulevard, SR 5/US-1, and SR A1A
- Bridge closures will be during non-peak hours, and will not occur during special events
- Work will be done in phases to minimize the impacts to the community
- Temporary lane closures to be required and will occur during non-peak hours
- Some activities will occur during night hours
- Pedestrian traffic will be maintained on the side of the bridge opposite from any ongoing construction
- Access to properties on both sides of the bridge will be maintained at all times
- Marine vessel traffic will be maintained with possible closure on half the