SONOVOID BRIDGE REPAIR/REHABILITATION BROWARD COUNTY-WIDE

Financial Number: 449243-1-52-01

Segment Work Length: 0.040 miles

Project Length: 0.161 miles

Purpose of Project: This project is to address independent slab movement - between Sonovoid slab units using ultra high-performance concrete joint repair at two (2) bridge locations in Broward County, Florida.

FPID# 449243-1-52-01 consists of two (2) locations and two (2) bridge structures:

  • Bridge Number 860001 – SR 5/US 1 over Dania Cut-off Canal
  • Bridge Number 860591 – SR 848/Stirling Road over Canal C-10

Public Meeting Workshop: No public information meeting is scheduled for this project.

Projected Letting: July 2025

Start Date: Fall 2025

Completion Date: Fall 2026

Estimated Construction Cost: $3.5 Million

Scope of Work:

PROPOSED IMPROVEMENTS — Bridge Number 860001 - SR 5/US 1 over Dania Cut-off Canal

  • Address independent slab movement between Sonovoid slab units using Hydrodemolition followed by ultra high-performance concrete (UHPC) joint repair along the longitudinal joints.
  • Mill existing asphalt along bridge between the curb lines
  • Resurface bridge with an asphalt overlay between the curblines.
  • Remove and replace existing expansion joints and headers with a polymeric joint header with poured joint and backer rod.

PROPOSED IMPROVEMENTS — Bridge Number 860591 – SR 848/Stirling Road over Canal C-10

  • Address independent slab movement between Sonovoid slab units using Hydrodemolition followed by ultra high-performance concrete (UHPC) joint repair along the longitudinal joints.
  • Mill existing asphalt along bridge between the curb lines
  • Resurface bridge with an asphalt overlay between the curblines.
  • Remove and replace existing expansion joints and headers with a polymeric joint header with poured joint and backer rod.

Construction Impacts:

  • At least one through lane will remain open at all times.
  • All work will be done in phases to reduce the impacts of construction on the community.
  • Pedestrian traffic will be maintained at all times.
  • Access to businesses and residences will be maintained at all times.
  • Maintain passenger access to and from bus stops during construction.

Contact Information:
Para información y preguntas en Español, por favor llame al (954) 777-4302.

 
 
 
Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express
zero