Financial Number: 446372‐1‐52‐01
Project Length: 2.05 Mile
Project Limits: From Oleander Drive to west of South 61st Avenue
Public Meeting: Date: Wednesday, August 31, 2022, at 6:00 p.m.
Project Purpose: To extend the service life of the roadway by repaving and restriping
Projected Letting: July 2023
Construction Start Date: Fall 2023
Completion Date: Fall 2025
Estimated Construction Cost: $3.4 Million
Scope of Work:
- Resurface and restripe roadway pavement
- Upgrade curb ramps to meet current standards
- Upgrade signs and pavement markings
- Upgrade existing signals at intersections
- Upgrade signalized intersection lighting with Light Emitting Diode (LED) luminaires
- Minor drainage improvements
Construction Impacts:
- Construction will be done in phases to reduce the effects of construction on the community.
- Local impacts such as events, holidays and peak seasons will be considered.
- Short-term lane closures will occur during non‐ peak hours on non-event days:
- Daytime: 9:30 a.m. to 3:30 p.m.
- Nighttime: 9:00 p.m. to 7:00 a.m.
- Access to businesses and residences will be maintained at all times.
Contact Information:
Documents:
State Road 25/US 27 from SR 818/Griffin Road to Truck Stop Flyer
|