SR 93/I-75 from Sheridan Street to South of I-595 Resurfacing Project

Financial Number: 437832-2-52-01

Project Length: 5.7 miles

Project Limits: SR 93/I-75 from Sheridan Street to south of I-595

Start Date: August 3, 2021

Completion Date: Summer 2022

Contractor: OHL USA, Inc.

Estimated Construction Cost: $7,949,000

Scope of Work:
Project improvements include milling and resurfacing along SR 93/I-75 between Sheridan Street and south of I-595, installing guardrail and double-face guardrail throughout the project limits, and installing signs and flashing beacons to alert wrong way drivers at the SR 93/I-75 southbound exit ramp to Griffin Road.

Documents:

PDF IconSR 93/I-75 from Sheridan Street to South of I-595 Resurfacing Project

 

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

During Construction

 


Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express