Financial Number: 443591‐1‐52‐01
Project Length: 0.327 miles
Project Limits:
- State Road (SR) 7/US 441 at Oakes Road
In-Person Public Information Meeting:
Virtual Public Information Meeting:
- Date: Thursday, January 27, 2022, from 5:00 p.m. to 6:00 p.m.
- Virtual Attendees: Please use the following link to register and receive a link to join the meeting: https://fdot.cc/SR7-US441-at-Oakes-Rd or call toll free if you prefer to dial in by phone: +1(866) 901‐6455 Access Code: 783‐182‐189
Projected Letting: Winter 2023
Start Date: Spring 2023
Completion Date: Fall 2023
Estimated Construction Cost: $2.5 M
Scope of Work:
- Widening the eastbound approach on Oakes Road to provide dual left turn lanes and an exclusive right turn lane.
- Striping of buffered bicycle lanes along southbound SR 7 from Oakes Road to south of the I‐595 interchange.
- Milling and resurfacing.
- Reconstructing existing sidewalk along Oakes Road and curb ramps to meet ADA standards.
- Improvements to lighting, signalization, signing and pavement markings.
- Replacement of the existing strain poles to mast arms
Construction Impacts:
- Lane closures will be used during construction. One lane in each direction will be maintained at all times.
- There will be no complete road closures.
- Access to businesses and residences will be maintained at all times.
Documents:
Oakes Rd VPM Presentation
Oakes Road Flyer January 2022