FinanciaNumbers: 447543-1-52-01
Project length: 0.978 Miles
Project Limits: SR 814 / Atlantic Boulevard from east of Turnpike to east of NW 28th Avenue
Public Meeting: No public information workshop is scheduled for this project.
Projected Letting: Summer 2024
Start Date: Fall 2024
Completion Date: Spring 2025
Estimated Construction Cost: $850,000
Scope of Work:
- Retrofit existing FDOT light poles on the north side of SR 814/Atlantic Blvd with LED luminaires.
- Install new lighting system along the south side of SR 814/Atlantic Blvd
Construction Impacts:
- Work will be done in phases to reduce the inconvenience to the community.
- No full roadway closures are anticipated.
- Temporary single lane closures will occur during off peak hours to minimize impacts on traffic.
- Access to businesses and residents will be maintained at all times during construction.
Contact Information:
Project Map:
|