SR 732/Jensen Beach Causeway Mobility Improvements Project

Financial Number: 440473-1-52-01

Project Limits: 1.842 Miles

Project Length: SR 732/Jensen Beach Causeway from NE Indian River Drive to SR A1A

Start Date: September 19, 2023

Completion Date: Late 2024

Contractor: Carr Construction, LLC

Estimated Construction Cost: $3 million

Scope of Work:

The SR 732/Jensen Beach Causeway project improvements consist of milling and resurfacing the existing roadway, replacing damaged sidewalk, upgrading pedestrian curb ramps to meet Americans with Disabilities Act (ADA) standards, upgrading signing and markings to provide buffered bicycle lanes, and replacing the existing bridge lighting, pendant lighting, and decorative pier lights.

Point of Contact:

"Para información y preguntas en Español, por favor llame al (954) 777-4302."

Documents:

PDF IconJBC Project Flyer

 

Project Photos

Pre-Construction

Click to view enlarged version/details

During Construction

Click to view enlarged version/details
8 Mounting electrical junction boxes, Feb. 2024 Crew was clearing blocked conduit for installation of new electrical wires, Jan. 2024 Clearing blocked conduit for installation of new electrical wires, Jan. 2024
Contractor started to erect and tie re bar for installation of the new light pole pedestals on the Jensen Beach Causeway.   Feb. 2024 Began to erect and tie re bar for installation of the new light pole pedestals on the Jensen Beach Causeway.   Feb. 2024 Pouring structual concrete for new light pole pilasters, Mar. 2024Placing of forms for new light pole foundations, Mar. 2024
Removing of the forms after structural concrete was poured, Mar. 2024 Re installing railing, eastbound, April 2024 New light pole installation, eastbound, April 2024 Westbound light pole removal, May 2024
Sidewalk and bike installation, May 2024 Installation of the new underdeck lighting, June 2024 Subcontractor prepares to install the new underdeck lighting, June 2024 Pouring of structural concrete light pole pedestals, July 2024
Installation of rebar for new light pole pedestals, July 2024 Setting of forms for the pouring of concrete for new light pole pedestals, July 2024 Completing guardrail installation, July 2024Reinstallation of a railing following concrete pour, Aug. 2024
New light pole installation on the north side of the bridge, Aug. 2024Concrete Pour for new light pole foundations on north side of the bridge, Aug. 2024Nighttime milling operation, September. 2024Asphalt placement on the bridge, September. 2024
Concrete crew finishing slipform class II conctrete pour for barrier wall coping junction slab located on SR 710 Warfield Blvd at SW Tommy Clements Street, August. 2024Rebar tied in place for slipform concrete barrier wall and junction coping slab.  Located at left roadway on NB & WB SR 710 Warfield Blvd at SW Tommy Clements Street, August. 2024Concrete slipform operation for class II conctrete pour on concrete barrier wall coping junction slab located on SR 710  Warfield Blvd at SW Tommy Clements Street, August. 2024Steel tied for concrete barrier wall, September. 2024
New guardrail installation at SW Tommy Clements Street, September. 2024





Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone